Projektleírás

From April 2013 the water quantity produced by the wells started to drop. The missing quantity was supplied from the grid. This trend led to shutting down even the last well in October
2013. Since then, the meat plant has been meeting its water demand exclusively from the grid.

During the recommissioning the main problem to be solved was the high concentration of iron, manganese, and ammonium in two of the three wells, and the high arsenic content in one well. In addition, water in all three wells has a high Na content.

Részletek

Szerződés tárgya:
Recommissioning the existing wells, design and construction of a new facility
Helyszín:
Szolnok, Hungary
Évszám:
2014

Jellemzők

Recommissioning three existing wells and the design and construction of the new water treatment facility (1,920 m2 including the area of the wells, water treatment facility, storage tank, and water tower)

Képek a projektről

További projektek

Helyszín: Kecskemét, Hungary
Év: 2009-2024
We were involved in the preparation of permit, construction, installation and implementation plans for WERK1-2 projects, as well as site engineering tasks.
Helyszín: Kecskemét, Hungary
Év: 2013
Complete building engineering: comfort ventilation and extraction systems.
Helyszín: Uppsala, Sweden
Év: 2006
3D design of pharmaceutical technology plant, using the MicroStation TriForma and Bentley Plant Space Design Series software